HOME  HELP  HOW TO ADVERTISE  SI
Useful Links
Landmarks
1905 Bombay Electric Supply & Tramways Co. Ltd. was formed. B.E.S.T. CO. Acquired from British Electric Traction Co. A Power House with 1100 HP generator & 107 consumers.
   
1907 Steam power generation started at Wari Bunder (4300 KW).
   
1912 Kussara generating station commissioned.
   
1916 Purchase of power from TATA's began.
   
1925 Generation discontinued.
   
1931 Remote control of D.C. Substations began.
   
1947 Management taken over by B.M.C.
   
1949 First 22 KV. receiving station commissioned at Apollo and Grand Road.
   
1951 D.C. to A.C. conversion started. 
   
1954 Primary distribution voltage changed from 5.5 KV to 6.6  KV. 
   
1955 ABCB introduced.
   
1957 Maximum Demand reached 100 MW.
   
1958 Intercom introduced.
   
1960 VHF system installed. 
   
1964 Tramcars discontinued.
   
1967 Single meter tariff introduced.
   
1967 Supervisory Remote Control (SRC) system commissioned.
   
1968 Gas Lamps eliminated.
   
1969 Material testing activity was started.
   
1970 Maximum Demand reached 200 MW.
   
1970 Units purchased reached 1000 MUS.
   
1970 Simha schemes introduced.
   
1971 PVC cables introduced in system.
   
1971 Epoxy cable jointing introduced.
   
1977 Primary Dist. voltage changed over from 6.6 KV to 11 KV-First phase (South)
   
1981 Minimum Oil Circuit Breakers Introduced.
   
1982 High Pressure Sodium Vapour Lamps Introduced. 
   
1982 Computerised Electric Bills Introduced.
   
1982 XLPE Cables Introduced. 
   
1982 Primary Transformation  Voltage Changed Over from 22kV  To 33 kV. at Apollo & Hutatma Chowk  Receiving Sub Stations. 
   
1985  Vacuum Circuit Breakers Introduced.
   
1985  Sf6 Switchgear Introduced.
   
1986 Maximum Demand Reached 400 MW.
   
1986 Units Purchased Reached 2000 Million Units.
   
1989  110kV/11kV Sub Station  Commissioned With GIS At Nariman Point.
   
1993 Microwave Communication System Introduced.
   
1993 Khetwadi 110kV/33kV Receiving Sub Station Commissioned.
   
1994 Electronic  Meters Introduced In The System.
   
1994 Primary Distribution Voltage Changed Over From 6.6kV To 11kV-First Phase (North)
   
1994 Primary Transformation Changed Over From 22kV To 33kV (Dharavi).
   
1994 Energy Audit Department Formed.
   
1995 Computer Application Department Formed.
   
1995 Generation Cell Formed.
   
1995 New Intercom System Introduced. 
   
1996 Maximum Demand Reached 600 MW.
   
1996 Units Purchased Reached 3000 Million Units.
   
1997 Ward-wise Functioning Of Commercial Departments started .
   
1997 Switched L.V. Capacitors Installed.
   
1997 Tower Lighting Installed At Chowpatty.
   
1997 11kv Change Over In South Zone Completed.
   
1997 System Power Factor Reached Above 0.98.
   
1997 System Maximum Demand In MVA Reduced Due To Improvement Of Power  Factor 
   
1997 One Window Redressal System Started for 2 KW. loads 
   
1998 RKVAH Charges  Introduced For Agreemental Tariffs. 
   
1998 One Window Redressal System Extended To 25 KW.
   
1999 Advance Payment Scheme Introduced.
   
1999 110KV Backbay Receiving Substation Commisioned.
   
2001 Achieved 100% group control of street lighting lamps
   
2001 2001 FRP Mini pillars are introduced in system
   
2002 Automatic switched capacitor introduced
   
2003

System maximum demand reached 700 MW

   
2003

Consumer Grievance Redressal Forum set up

   
2005

System maximum demand reached 800 MVA

   
2005

Units purchased reached 4000MUs

   
2006

Amnesty scheme for recovery of long pending electricity bills arrears was launched first.

   
2006

A separate cell established for procurement of power and analysis of Availability Based Tariff and Long Term Power Procurement Plan (LTPPP)

   
2006

First time MERC tariff implemented

   
2006

Metering for street lighting provided

   
2006

Started issuing colourful electricity bills with bar coding facility

   
2006

O & M (NE) Division established

   
2006

Automatic Cheque acceptance machine against electricity bills introducing on trial basis.

   
2007

 

   
2008

 

   
2009

Digitization project

   
2010 1)Implementation of three remote terminal at system control at Dadar, Pathakwadi and Colaba.
 2)Commissioning of Morarji Mill (33KV / 415 V) RSS
Copyrights ?All Rights Reserved
Cuffie monster beats Monster dr dre Casque beats Beats by dre Christian Louboutin Outlet Discount longchamp bags